As part of the ongoing Ferst Drive Realignment Project, the following work will affect vehicular and pedestrian circulation in the areas noted. No road closures are planned; however, traffic will be flagged through active work zones. Commuters should expect delays.
Jul 10, 2025
As part of the ongoing Ferst Drive Realignment Project, the following work will affect vehicular and pedestrian circulation in the areas noted below. No road closures are planned; however, traffic will be flagged through active work zones. Commuters should expect delays.
Pedestrian and Roadway Disruptions:
Beginning Friday, July 11
- The southeast corner of Fifth Street and Techwood Drive will reopen to pedestrian traffic.
- Demolition will begin on the southwest corner of Fifth Street and Techwood Drive.
- The sidewalk on the south side of Fifth Street between Techwood Drive and Fowler Street will close through July 25.
Monday, July 14, Through Wednesday, July 23
- Milling operations will take place along Fifth Street and Ferst Drive, from Russ Chandler Stadium to the Fifth Street Bridge, July 14 – 16.
- Milling of failing sections of asphalt on Fowler Street and Fourth Street is scheduled for July 16. To facilitate this work, parking along Fowler Street will be closed July 15 – 23. Please refer to the map for parking impacts.
- Paving will occur along Fifth Street and Ferst Drive July 21 – 23.
- Paving will be completed on Fowler Street and Fourth Street on July 23.